Mustla Bridge, Estonia
4.2m high MSE bridge abutments
International
Bridge abutment
Mechanically stabilised earth
Retaining wall
Redi-Rock
I delivered the design of two 4.2m high segmental precast concrete block abutments for the new bridge on the Tallinn to Tartu highway. When a change created a conflict with the bridge piers I avoided delays by creating a custom facing detail with the manufacturer that transmitted the pressure on the facing around the pier. The walls were completed 4 weeks ahead of schedule.